Nebius plans $40B 2027 buildout as Microsoft deal slips
2026-11-13 · TechCrunch
Neocloud company Nebius laid out $40 billion in planned 2027 spending on its Nov. 12 third-quarter call, far more than Wall Street expected. TechCrunch notes the plan rests on a string of projects already showing cracks.
Nebius intends to fund the buildout with customer prepayments and loans backed by customer contracts, essentially using the future value of its data centers to pay for building them. The risk is that delays or cancellations pile up costs while pushing revenue out. CEO Arkady Volozh said on the call that building at this scale is hard and delays are part of the industry right now: 'We are not immune.'
Microsoft is the clearest example. Its contract, worth up to $19.4 billion, covers a Vineland, New Jersey data center that is months behind; only just over half the capacity is planned for delivery by year-end, with the rest in Q2 2027. Nebius says site operator DataOne wound down temporary generation faster than expected as it switches to Bloom Energy fuel cells. Per Nebius's summary, Microsoft can terminate affected service after a grace period if dates are missed and no alternative capacity is offered, and the contract includes late-delivery penalties. Nebius did not say whether Microsoft agreed to new dates, and Microsoft has not publicly canceled anything.
TechCrunch adds that in August Floodlight found at least 45 gas generators at the site without permits, leading to a $1.1 million fine, and neighbors have sued over noise. Customer prepayment and contract-backed financing speed expansion, but power and delivery capability are becoming the bigger bottleneck, and reports suggest Microsoft is cooling on late neocloud deals.