Envision: world's first commercial 800V DC data center
2026-11-04 · Tom's Hardware
Tom's Hardware reports Envision Energy says it completed the world's first commercial data center deployment of an integrated 800V DC power system, using its Dubhe Controller and Dubhe Energy Foundation Model, tested since August at the Galaxy AI data center in Ulanqab, Inner Mongolia.
Instead of several conversion stages, it uses a solid-state transformer to turn 10kV medium-voltage AC directly into an 800V DC bus. Three pillars: stable SST conversion, battery storage with second-scale support and minute-scale backup, and millisecond coordination between the two to absorb GPU load swings locally.
The company says this enables denser AI racks, less copper and cabling, and fits renewables. Galaxy will scale to 3GW and eventually up to a million accelerators; Envision also plans it for 'Mission Gobi', targeting 5GW of green AI data centers in deserts by 2030. Performance claims are the company's own and unverified.