Texas Suspends 17 Data Center Construction Permits
2026-10-24 · Tom's Hardware
Texas has suspended construction permits for 17 data center projects and taken offline the web portal that approved them automatically. Per Tom's Hardware, citing 404 Media, the state environmental agency TCEQ's STEERS filing system now says it is temporarily shut down so staff can check whether each application relates to a data center.
Governor Greg Abbott asked in September for new data center permits to be halted and for roughly 1,800 projects to be audited, citing power use and generation, water consumption and community impact. But watchdog groups FracTracker Alliance and Public Citizen published reports showing more than two dozen permits were still issued a month later. A FracTracker researcher said projects for OpenAI and Amazon passed through the system earlier this week.
All 17 suspended permits are stormwater construction permits, a step required before construction companies level and raise the ground, and one that nearly every Texas project must pass. The report likened STEERS to a rubber stamp that approves filings without human review.
It is part of a wider shift: New York signed a one-year ban on data centers over 50 megawatts in July, Amazon dropped four planned Northern Virginia facilities after local backlash, and President Trump called in October for data center operators to pay communities a dividend. AI demand is driving construction, but water, power and local acceptance are drawing closer scrutiny.