Microsoft reportedly exits UK's largest AI supercomputer
2026-10-21 · The Register
The Register, citing a Sunday Telegraph report, says Microsoft pulled out of plans for Britain's largest AI supercomputer because the government-backed project has no electricity to run it. Microsoft reportedly terminated its agreement with UK AI infrastructure startup Nscale for a Loughton, Essex datacenter; Microsoft did not respond, so this is press reporting.
When announced in September 2025, the plan was to pack 23,040 Nvidia GB300 GPUs into a 50 MW facility, expandable to 90 MW, for Microsoft's Azure, with first chips in early 2027. Nscale pitched it as the UK's largest sovereign AI datacenter.
The crux is power. The Guardian reported last month that UK Power Networks warned Nscale the grid capacity might not be available until the 2030s. UKPN told The Register it can't discuss individual connections but that many datacenters can connect to its distribution network while awaiting works on the national transmission network it doesn't own.
Nscale says it remains committed to Loughton and the UK, is exploring alternative power and other sites, that its Microsoft relationship remains strong and that the grid issue doesn't affect other contracts. The Register notes the government had included the project in Microsoft's £22 billion UK investment announcement.
The case shows the AI compute bottleneck shifting from chips to power and grid connection.