SemiAnalysis: Local bans delay only 2.3GW of data centers
2026-10-18 · Tom's Hardware
SemiAnalysis published an analysis on October 17 of local data center moratoriums across the US. The common belief is that they are choking the buildout, but the firm says its 2027 forecast has barely moved in 12 months: 38GW of IT capacity is expected online that year, more than double 2026.
As relayed by Tom's Hardware, the firm tracks more than 400 local instruments in 17 states. About 21GW sits in moratorium areas, but only roughly 2.3GW is likely to slip. Enacted local moratoriums cover about 20GW with around 1.5GW delayed, and New York's pause adds 0.8GW. Four states acted within two months this summer: New York, Texas, Pennsylvania and Oregon.
The report gives several reasons for the weak effect. Moratoriums usually freeze new applications without revoking existing approvals; short ones can expire before later projects need permits; and litigation or equipment lead times may already set the schedule. A pause delays delivery only if it reaches the parcel, is in force, overlaps the timeline and cannot be worked around. Michigan has 45 enacted moratoriums but almost no exposure, and a Google campus there sits on land already zoned for data processing.
Some bans do work: a Pennsylvania township paused before NorthPoint filed for a special exception, pushing local approval to next year. The 2.3GW figure also excludes a Texas pause on data center permits that is expected to last until ERCOT finishes its review in mid-December. SemiAnalysis concludes that moratoriums could delay the buildout but are not yet at scale. The numbers come from a single research firm using its own methods.